UPM Plattling / MD Papier GmbH

New construction of the paper mill Plattling Papier PM1

Projektdetails

In the course of the new construction of the paper machine PM1, SCHUSTER engineering planned the complete infrastructure.

  • Access road with logistics areas, including sewer and hydrant network
  • Wood storage area with 34.000 m²
  • Railway connection for finished goods storage, stock preparation, pulp storage and timber storage area with a length of approx. 3.5 km and several switches
  • Outdoor facilities with infiltration and planting